Sheridan's industrial land has a past, and any metal building we put on it starts with what is in the ground. The South Platte-side business park off U.S. 85 includes auto salvage, a recycling center, a lumber yard, auto repair and light manufacturing uses. The city planned Phase 1 and Phase 2 environmental assessments of those parcels through EPA's Targeted Brownfield Assessment program to estimate remediation costs. We build here with that in mind, and we ask for the environmental reports before we price a foundation.
We erect rigid frame steel buildings for repair shops, light manufacturers, storage users and yard operators. Those users want a dry, secure building at a firm cost, and they usually have equipment to protect. A metal building gives clear span for vehicles and machinery, with wall and roof panels that go up in days rather than weeks.
We name the load package and lead time up front, and we separate site and soil costs from the steel so you can compare bids honestly.
Soil history, floors and what we ask first
On a site with prior industrial use, the questions come before the drawings. Is there an environmental assessment? Are there areas flagged for contamination or controls? Where did the previous buildings sit, and what is under old slabs? These answers shape footing depth, vapor control under the slab and where spoil can go. We cannot price around guesses.
Close to the river, groundwater can sit high and soils can be soft or mixed. The geotechnical report drives the foundation type. If it calls for engineered fill or deeper footings, that cost is real, and it belongs in the budget before the steel is ordered. See our anchor bolts and foundations page for how we coordinate that work.
Soil handling and site safety
When soil may be affected, the plan for excavation matters: who tests, where material goes and what is documented. We coordinate with your environmental consultant and keep records. Every crew on site follows the plan the consultant and owner set, and we do not move suspect soil without direction.
On the steel side, the safety plan covers crane position, overhead lines, fall protection and neighbors. Sheridan is a small city of 2.29 square miles that borders Englewood and Denver, so many sites sit close to other businesses and homes. We keep deliveries tight, control dust and keep the street clean.
How we handle a brownfield-adjacent job
We start by sorting what the building needs from what the site needs. The building: frame, panels, doors, insulation. The site: remediation, imported fill, utilities, paving. We price them separately and tell you which items could change if the environmental findings change. This is a clean way to protect your budget.
Then we sequence. Foundation work follows approvals, steel is released after the geotechnical and environmental questions are settled, and erection goes fast. Time on site is short, which is useful when the neighbors are close and the lot is small.
What we manage
We schedule and inspect the crews that erect the structural frame, install girts and purlins, hang roof and wall panels, set trim, and install overhead doors and man doors. We handle insulation and liner panels for finished interiors. When the project calls for a floor above, we add a mezzanine to the frame design.
Fewer subcontractors on the envelope means fewer gaps. If you are retrofitting an older building at the edge of the site, the re-skin and retrofit crews we coordinate can replace failed panels and leaky roofs without rebuilding the frame. That can be the right first step on an older shop.
Buildings and users that fit
Repair and service shops, light manufacturing bays, parts warehouses, equipment storage and yard offices. Fleet and automotive users find the clear span attractive. U.S. 85 runs along Sheridan's eastern edge, U.S. 285 runs east to west through the city, and State Highway 88 (South Federal Boulevard) runs the length of the city from Englewood to Denver, giving trucks quick routes in several directions.
The Oxford-City of Sheridan RTD light rail station has its only entrance in Englewood, which tells you how closely the two cities are tied. If you are comparing sites, look at Englewood and Denver too. Our manufacturing page and flex and light industrial page show typical layouts.
Where the money goes
Foundation and site work often exceed the cost of the envelope on small lots with history. Soil replacement, vapor barriers, drainage and utilities are the big items. The steel package is the predictable part, driven by span, height and loads. We keep that number honest and tell you what could move.
To protect your budget, order environmental and geotechnical work before you finalize the building. A modest cost for reports prevents a large change order later. We hold off on steel release until you are comfortable with the risk, even if it delays the start.
Timing around reports and approvals
Schedule on a site like this has an order that cannot be skipped. First, reports and findings. Second, foundation design and permits. Third, steel release and pad work together. Fourth, erection. If reports come back clean, the sequence moves fast. If they come back with conditions, the sequence stretches, and we tell you where.
We keep steel lead time in view, because fabrication slots can be held while approvals finish if the design is stable. We keep the crew free for your date when the pad is ready. Owners who want to start a lease on a date should treat reports as the start of the project, not an item to do after contract signing.
Price a Sheridan steel building
Send the address, the use and any environmental or soils reports you have. We will name the load package and lead time and keep the site costs on their own lines.
Related Service Areas
Next Step
Plan This Project With Us
Tell us about the site, the building and the schedule, and we will set up a review of scope, schedule, permits and inspections.
Common Questions
Review any environmental assessments, ask the seller about past uses and hire a consultant if the history is unclear. Sheridan used EPA's Targeted Brownfield Assessment program to plan Phase 1 and Phase 2 assessments for parcels in its South Platte-side business park. Get the foundation design from a geotechnical engineer too.
Yes, when the environmental and geotechnical work is done and the owner has a plan for soil. We build the structure and coordinate with your consultant on excavation, vapor control and documentation. We do not make environmental decisions, and we do not pour until approvals are in hand.
U.S. 85 runs along the eastern edge, U.S. 285 runs east to west through the city, and State Highway 88 runs the length of the city from Englewood to Denver. Trucks can reach several corridors quickly, which is useful for service and parts businesses.
By pricing the steel, the site and the soil as separate lines and by asking for reports early. We show which items depend on unknowns and give a range for each. You can then decide where to take risk.
Often, when the frame is sound. Replacing roof and wall panels, insulation and doors can restore an older building at a fraction of the cost of new, and it avoids new foundation work. We inspect the frame and give you an honest comparison.
Yes. A clear-span shell with the right floor loads, power service and ventilation can host fabrication, assembly and light production. Tell us about your equipment and process so we can size the slab, the doors and any crane rail. Zoning and permit review are separate steps we help you prepare for.
PROJECT REVIEW
Tell us about the site, the building and the schedule, and we will set up a review of scope, schedule, permits and inspections.
SERVICE AREAS
See the Colorado communities where we plan and manage pre-engineered metal building construction.